{"id":877,"date":"2025-04-01T15:30:00","date_gmt":"2025-04-01T15:30:00","guid":{"rendered":"https:\/\/daterra.de\/?p=877"},"modified":"2026-04-12T20:21:57","modified_gmt":"2026-04-12T20:21:57","slug":"construction-of-f90-fire-wall","status":"publish","type":"post","link":"https:\/\/daterra.de\/en\/errichtung-f90-brandwand\/","title":{"rendered":"Fire Protection Expertise in Data Centers \u2013 Construction of an F90 Fire Wall During Ongoing Operation"},"content":{"rendered":"<div data-elementor-type=\"wp-post\" data-elementor-id=\"877\" class=\"elementor elementor-877\" data-elementor-post-type=\"post\">\n\t\t\t\t<div class=\"elementor-element elementor-element-89c2ccb e-flex e-con-boxed e-con e-parent\" data-id=\"89c2ccb\" data-element_type=\"container\" data-e-type=\"container\">\n\t\t\t\t\t<div class=\"e-con-inner\">\n\t\t\t\t<div class=\"elementor-element elementor-element-ed8b26d elementor-widget elementor-widget-text-editor\" data-id=\"ed8b26d\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"text-editor.default\">\n\t\t\t\t\t\t\t\t\tModernizing active data centers requires the utmost precision. <strong>Daterra (formerly FM Service)<\/strong> implemented the construction of an F90 fire wall in a high-availability environment to secure the site sustainably. Through technical interface management, the solution was implemented without interrupting IT systems.\t\t\t\t\t\t\t\t<\/div>\n\t\t\t\t\t<\/div>\n\t\t\t\t<\/div>\n\t\t<div class=\"elementor-element elementor-element-fab9320 e-flex e-con-boxed e-con e-parent\" data-id=\"fab9320\" data-element_type=\"container\" data-e-type=\"container\">\n\t\t\t\t\t<div class=\"e-con-inner\">\n\t\t\t\t<div class=\"elementor-element elementor-element-7efa71a elementor-widget elementor-widget-heading\" data-id=\"7efa71a\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"heading.default\">\n\t\t\t\t\t<h2 class=\"elementor-heading-title elementor-size-default\">Services in the Project \u2013 Precise General Contracting for Maximum Security<\/h2>\t\t\t\t<\/div>\n\t\t\t\t<div class=\"elementor-element elementor-element-64522f1 elementor-widget elementor-widget-text-editor\" data-id=\"64522f1\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"text-editor.default\">\n\t\t\t\t\t\t\t\t\t<p>The implementation was carried out within a general contractor structure with precise control of all technical processes and interfaces. A specialized team of project managers, architects, and structural engineers ensured the professional execution of the fire protection measure. As the construction of the F90 wall directly interfered with the existing data center infrastructure, the coordination of 30 active specialists and six trades involved formed the core of the service.<\/p>\t\t\t\t\t\t\t\t<\/div>\n\t\t\t\t<div class=\"elementor-element elementor-element-98eda24 elementor-icon-list--layout-traditional elementor-list-item-link-full_width elementor-widget elementor-widget-icon-list\" data-id=\"98eda24\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"icon-list.default\">\n\t\t\t\t\t\t\t<ul class=\"elementor-icon-list-items\">\n\t\t\t\t\t\t\t<li class=\"elementor-icon-list-item\">\n\t\t\t\t\t\t\t\t\t\t\t<span class=\"elementor-icon-list-icon\">\n\t\t\t\t\t\t\t<svg aria-hidden=\"true\" class=\"e-font-icon-svg e-fas-chevron-right\" viewbox=\"0 0 320 512\" xmlns=\"http:\/\/www.w3.org\/2000\/svg\"><path d=\"M285.476 272.971L91.132 467.314c-9.373 9.373-24.569 9.373-33.941 0l-22.667-22.667c-9.357-9.357-9.375-24.522-.04-33.901L188.505 256 34.484 101.255c-9.335-9.379-9.317-24.544.04-33.901l22.667-22.667c9.373-9.373 24.569-9.373 33.941 0L285.475 239.03c9.373 9.372 9.373 24.568.001 33.941z\"><\/path><\/svg>\t\t\t\t\t\t<\/span>\n\t\t\t\t\t\t\t\t\t\t<span class=\"elementor-icon-list-text\"><strong>Taking over the general contractor function:<\/strong> Complete organization and control of the involved trades to ensure a smooth project flow.<\/span>\n\t\t\t\t\t\t\t\t\t<\/li>\n\t\t\t\t\t\t\t\t<li class=\"elementor-icon-list-item\">\n\t\t\t\t\t\t\t\t\t\t\t<span class=\"elementor-icon-list-icon\">\n\t\t\t\t\t\t\t<svg aria-hidden=\"true\" class=\"e-font-icon-svg e-fas-chevron-right\" viewbox=\"0 0 320 512\" xmlns=\"http:\/\/www.w3.org\/2000\/svg\"><path d=\"M285.476 272.971L91.132 467.314c-9.373 9.373-24.569 9.373-33.941 0l-22.667-22.667c-9.357-9.357-9.375-24.522-.04-33.901L188.505 256 34.484 101.255c-9.335-9.379-9.317-24.544.04-33.901l22.667-22.667c9.373-9.373 24.569-9.373 33.941 0L285.475 239.03c9.373 9.372 9.373 24.568.001 33.941z\"><\/path><\/svg>\t\t\t\t\t\t<\/span>\n\t\t\t\t\t\t\t\t\t\t<span class=\"elementor-icon-list-text\"><strong>Interdisciplinary Construction Management<\/strong> Continuous coordination of execution phases, taking into account structural and architectural requirements.<\/span>\n\t\t\t\t\t\t\t\t\t<\/li>\n\t\t\t\t\t\t\t\t<li class=\"elementor-icon-list-item\">\n\t\t\t\t\t\t\t\t\t\t\t<span class=\"elementor-icon-list-icon\">\n\t\t\t\t\t\t\t<svg aria-hidden=\"true\" class=\"e-font-icon-svg e-fas-chevron-right\" viewbox=\"0 0 320 512\" xmlns=\"http:\/\/www.w3.org\/2000\/svg\"><path d=\"M285.476 272.971L91.132 467.314c-9.373 9.373-24.569 9.373-33.941 0l-22.667-22.667c-9.357-9.357-9.375-24.522-.04-33.901L188.505 256 34.484 101.255c-9.335-9.379-9.317-24.544.04-33.901l22.667-22.667c9.373-9.373 24.569-9.373 33.941 0L285.475 239.03c9.373 9.372 9.373 24.568.001 33.941z\"><\/path><\/svg>\t\t\t\t\t\t<\/span>\n\t\t\t\t\t\t\t\t\t\t<span class=\"elementor-icon-list-text\"><strong>Scheduling and coordination:<\/strong> Detailed planning of time slots to maintain system availability throughout the construction period.<\/span>\n\t\t\t\t\t\t\t\t\t<\/li>\n\t\t\t\t\t\t\t\t<li class=\"elementor-icon-list-item\">\n\t\t\t\t\t\t\t\t\t\t\t<span class=\"elementor-icon-list-icon\">\n\t\t\t\t\t\t\t<svg aria-hidden=\"true\" class=\"e-font-icon-svg e-fas-chevron-right\" viewbox=\"0 0 320 512\" xmlns=\"http:\/\/www.w3.org\/2000\/svg\"><path d=\"M285.476 272.971L91.132 467.314c-9.373 9.373-24.569 9.373-33.941 0l-22.667-22.667c-9.357-9.357-9.375-24.522-.04-33.901L188.505 256 34.484 101.255c-9.335-9.379-9.317-24.544.04-33.901l22.667-22.667c9.373-9.373 24.569-9.373 33.941 0L285.475 239.03c9.373 9.372 9.373 24.568.001 33.941z\"><\/path><\/svg>\t\t\t\t\t\t<\/span>\n\t\t\t\t\t\t\t\t\t\t<span class=\"elementor-icon-list-text\"><strong>Integration of technical preparatory work<\/strong> Voting and carrying out the necessary preparatory work on the building technology to position the wall in accordance with standards.<\/span>\n\t\t\t\t\t\t\t\t\t<\/li>\n\t\t\t\t\t\t<\/ul>\n\t\t\t\t\t\t<\/div>\n\t\t\t\t\t<\/div>\n\t\t\t\t<\/div>\n\t\t<div class=\"elementor-element elementor-element-66255c8 e-flex e-con-boxed e-con e-parent\" data-id=\"66255c8\" data-element_type=\"container\" data-e-type=\"container\">\n\t\t\t\t\t<div class=\"e-con-inner\">\n\t\t\t\t<div class=\"elementor-element elementor-element-b556386 elementor-widget elementor-widget-heading\" data-id=\"b556386\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"heading.default\">\n\t\t\t\t\t<h2 class=\"elementor-heading-title elementor-size-default\">Project Highlights: Seamless integration of new fire compartments into existing architecture<\/h2>\t\t\t\t<\/div>\n\t\t\t\t<div class=\"elementor-element elementor-element-6f3a5bc elementor-widget elementor-widget-text-editor\" data-id=\"6f3a5bc\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"text-editor.default\">\n\t\t\t\t\t\t\t\t\t<p>The essential result of the measure is the seamless separation of the fire compartments from the bare ceiling to the bare floor. A crucial part of the implementation was the <strong>preparatory adaptation of the MEP infrastructure<\/strong>, to clear the space for the massive wall elements. Precise planning ensured the structural integrity was maintained while the new protective barrier was completed without functional limitations for the data center.<\/p>\t\t\t\t\t\t\t\t<\/div>\n\t\t\t\t\t<\/div>\n\t\t\t\t<\/div>\n\t\t<div class=\"elementor-element elementor-element-245fe36 e-flex e-con-boxed e-con e-parent\" data-id=\"245fe36\" data-element_type=\"container\" data-e-type=\"container\">\n\t\t\t\t\t<div class=\"e-con-inner\">\n\t\t\t\t<div class=\"elementor-element elementor-element-5f152ec elementor-widget elementor-widget-heading\" data-id=\"5f152ec\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"heading.default\">\n\t\t\t\t\t<h2 class=\"elementor-heading-title elementor-size-default\">Project Management: Six Months Coordinated Implementation of Technical Specifications<\/h2>\t\t\t\t<\/div>\n\t\t\t\t<div class=\"elementor-element elementor-element-c519f2e elementor-widget elementor-widget-text-editor\" data-id=\"c519f2e\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"text-editor.default\">\n\t\t\t\t\t\t\t\t\t<p>The realization followed a defined staging over a <strong>Six-month period<\/strong>. The opening was a <strong>in-depth inventory analysis<\/strong> infrastructure, as well as the building code review of fire protection requirements. In coordination between architecture and structural engineering, the positioning of the F90 wall was determined before the <strong>active construction phase in September<\/strong> started.<\/p>\n<p>In the implementation phase, Daterra managed the parallel processes as the general contractor. One focus was on <strong>Coordination of interfaces<\/strong>, to <strong>Relocation of technical trades<\/strong> to precisely integrate with the wall construction over time. On-site construction management ensured all steps were completed within the timeframe, allowing for completion in <strong>February with the final acceptance<\/strong> occurred.<\/p>\t\t\t\t\t\t\t\t<\/div>\n\t\t\t\t\t<\/div>\n\t\t\t\t<\/div>\n\t\t<div class=\"elementor-element elementor-element-72f2953 e-con-full e-flex e-con e-parent\" data-id=\"72f2953\" data-element_type=\"container\" data-e-type=\"container\" data-settings=\"{&quot;background_background&quot;:&quot;gradient&quot;}\">\n\t\t\t\t<div class=\"elementor-element elementor-element-08ea207 elementor-widget elementor-widget-heading\" data-id=\"08ea207\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"heading.default\">\n\t\t\t\t\t<h3 class=\"elementor-heading-title elementor-size-default\">Special Challenges \u2013 Construction During Operations Under Winter Conditions<\/h3>\t\t\t\t<\/div>\n\t\t\t\t<div class=\"elementor-element elementor-element-ac38843 elementor-widget elementor-widget-text-editor\" data-id=\"ac38843\" data-element_type=\"widget\" data-e-type=\"widget\" data-widget_type=\"text-editor.default\">\n\t\t\t\t\t\t\t\t\t<p>The greatest difficulty was carrying out the work during the <strong>Winter months <\/strong>while simultaneously protecting the sensitive environment. To ensure material quality and execution quality, Daterra built a <strong>heated protective tent<\/strong> directly above the work area. In parallel, the <strong>Ongoing operation<\/strong> of the data center, a dust-free and low-vibration working method to avoid jeopardizing the availability of IT systems. To meet the logistical requirements and to ensure the <strong>Workplace safety during work at height<\/strong> also came a comprehensive <strong>Safety and work scaffolding<\/strong> for use.<\/p>\t\t\t\t\t\t\t\t<\/div>\n\t\t\t\t<\/div>\n\t\t\t\t<\/div>","protected":false},"excerpt":{"rendered":"<p>Die Modernisierung aktiver Rechenzentren erfordert h\u00f6chste Pr\u00e4zision. Daterra (ehem. FM Service) realisierte die Errichtung einer F90-Brandwand in einem hochverf\u00fcgbaren Umfeld, um den Standort nachhaltig abzusichern. Durch technisches Schnittstellenmanagement wurde die L\u00f6sung ohne Unterbrechung der IT-Systeme umgesetzt. Leistungen im Projekt \u2013 pr\u00e4zise Generalunternehmerschaft f\u00fcr maximale Sicherheit Die Umsetzung erfolgte im Rahmen einer Generalunternehmerstruktur mit einer pr\u00e4zisen [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":2129,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[11],"tags":[],"class_list":["post-877","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-referenzen"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.5 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Case Study: F90 Brandwand im laufenden Betrieb<\/title>\n<meta name=\"description\" content=\"Projekt zur Errichtung einer F90 Brandwand im laufenden Betrieb: Bau im Winter mit Schutzma\u00dfnahmen sowie Verlegung bestehender TGA-Gewerke.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Case Study: F90 Brandwand im laufenden Betrieb\" \/>\n<meta property=\"og:description\" content=\"Projekt zur Errichtung einer F90 Brandwand im laufenden Betrieb: Bau im Winter mit Schutzma\u00dfnahmen sowie Verlegung bestehender TGA-Gewerke.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/\" \/>\n<meta property=\"og:site_name\" content=\"Daterra Datacenter Solutions GmbH\" \/>\n<meta property=\"article:published_time\" content=\"2025-04-01T15:30:00+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2026-04-12T20:21:57+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/wp-content\/uploads\/2026\/04\/F90_Brandwand.webp\" \/>\n\t<meta property=\"og:image:width\" content=\"800\" \/>\n\t<meta property=\"og:image:height\" content=\"600\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/webp\" \/>\n<meta name=\"author\" content=\"s.kasprzyk\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"s.kasprzyk\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/\"},\"author\":{\"name\":\"s.kasprzyk\",\"@id\":\"https:\\\/\\\/daterra.de\\\/#\\\/schema\\\/person\\\/ef19e68fcacaf8c388fddd7349562d1d\"},\"headline\":\"Brandschutz-Expertise im Rechenzentrum \u2013 Errichtung einer F90 Brandwand im laufenden Betrieb\",\"datePublished\":\"2025-04-01T15:30:00+00:00\",\"dateModified\":\"2026-04-12T20:21:57+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/\"},\"wordCount\":474,\"publisher\":{\"@id\":\"https:\\\/\\\/daterra.de\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/daterra.de\\\/wp-content\\\/uploads\\\/2026\\\/04\\\/F90_Brandwand.webp\",\"articleSection\":[\"Referenzen\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/\",\"url\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/\",\"name\":\"Case Study: F90 Brandwand im laufenden Betrieb\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/daterra.de\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/daterra.de\\\/wp-content\\\/uploads\\\/2026\\\/04\\\/F90_Brandwand.webp\",\"datePublished\":\"2025-04-01T15:30:00+00:00\",\"dateModified\":\"2026-04-12T20:21:57+00:00\",\"description\":\"Projekt zur Errichtung einer F90 Brandwand im laufenden Betrieb: Bau im Winter mit Schutzma\u00dfnahmen sowie Verlegung bestehender TGA-Gewerke.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/#primaryimage\",\"url\":\"https:\\\/\\\/daterra.de\\\/wp-content\\\/uploads\\\/2026\\\/04\\\/F90_Brandwand.webp\",\"contentUrl\":\"https:\\\/\\\/daterra.de\\\/wp-content\\\/uploads\\\/2026\\\/04\\\/F90_Brandwand.webp\",\"width\":800,\"height\":600,\"caption\":\"F90 Brandwand\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/daterra-gmbh-98pq1olwan.live-website.com\\\/errichtung-f90-brandwand\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/daterra.de\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Brandschutz-Expertise im Rechenzentrum \u2013 Errichtung einer F90 Brandwand im laufenden Betrieb\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/daterra.de\\\/#website\",\"url\":\"https:\\\/\\\/daterra.de\\\/\",\"name\":\"Daterra Datacenter Solutions GmbH\",\"description\":\"Sustainable. Efficient. Competent.\",\"publisher\":{\"@id\":\"https:\\\/\\\/daterra.de\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/daterra.de\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/daterra.de\\\/#organization\",\"name\":\"Daterra Datacenter Solutions GmbH\",\"url\":\"https:\\\/\\\/daterra.de\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/daterra.de\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/daterra.de\\\/wp-content\\\/uploads\\\/2026\\\/03\\\/Daterra_Logo-2.png\",\"contentUrl\":\"https:\\\/\\\/daterra.de\\\/wp-content\\\/uploads\\\/2026\\\/03\\\/Daterra_Logo-2.png\",\"width\":580,\"height\":191,\"caption\":\"Daterra Datacenter Solutions GmbH\"},\"image\":{\"@id\":\"https:\\\/\\\/daterra.de\\\/#\\\/schema\\\/logo\\\/image\\\/\"}},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/daterra.de\\\/#\\\/schema\\\/person\\\/ef19e68fcacaf8c388fddd7349562d1d\",\"name\":\"s.kasprzyk\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/44fc54a0422931acf7970831a509dac2cc2d887f75e2fff4e0a12e08e6bc5d36?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/44fc54a0422931acf7970831a509dac2cc2d887f75e2fff4e0a12e08e6bc5d36?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/44fc54a0422931acf7970831a509dac2cc2d887f75e2fff4e0a12e08e6bc5d36?s=96&d=mm&r=g\",\"caption\":\"s.kasprzyk\"},\"sameAs\":[\"https:\\\/\\\/daterra.de\"]}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Case Study: F90 Fire Wall in Operation","description":"Project for the construction of an F90 fire-resistant wall in ongoing operation: Construction in winter with protective measures and relocation of existing building services.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/","og_locale":"en_US","og_type":"article","og_title":"Case Study: F90 Brandwand im laufenden Betrieb","og_description":"Projekt zur Errichtung einer F90 Brandwand im laufenden Betrieb: Bau im Winter mit Schutzma\u00dfnahmen sowie Verlegung bestehender TGA-Gewerke.","og_url":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/","og_site_name":"Daterra Datacenter Solutions GmbH","article_published_time":"2025-04-01T15:30:00+00:00","article_modified_time":"2026-04-12T20:21:57+00:00","og_image":[{"width":800,"height":600,"url":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/wp-content\/uploads\/2026\/04\/F90_Brandwand.webp","type":"image\/webp"}],"author":"s.kasprzyk","twitter_card":"summary_large_image","twitter_misc":{"Written by":"s.kasprzyk","Est. reading time":"3 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/#article","isPartOf":{"@id":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/"},"author":{"name":"s.kasprzyk","@id":"https:\/\/daterra.de\/#\/schema\/person\/ef19e68fcacaf8c388fddd7349562d1d"},"headline":"Brandschutz-Expertise im Rechenzentrum \u2013 Errichtung einer F90 Brandwand im laufenden Betrieb","datePublished":"2025-04-01T15:30:00+00:00","dateModified":"2026-04-12T20:21:57+00:00","mainEntityOfPage":{"@id":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/"},"wordCount":474,"publisher":{"@id":"https:\/\/daterra.de\/#organization"},"image":{"@id":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/#primaryimage"},"thumbnailUrl":"https:\/\/daterra.de\/wp-content\/uploads\/2026\/04\/F90_Brandwand.webp","articleSection":["Referenzen"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/","url":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/","name":"Case Study: F90 Fire Wall in Operation","isPartOf":{"@id":"https:\/\/daterra.de\/#website"},"primaryImageOfPage":{"@id":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/#primaryimage"},"image":{"@id":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/#primaryimage"},"thumbnailUrl":"https:\/\/daterra.de\/wp-content\/uploads\/2026\/04\/F90_Brandwand.webp","datePublished":"2025-04-01T15:30:00+00:00","dateModified":"2026-04-12T20:21:57+00:00","description":"Project for the construction of an F90 fire-resistant wall in ongoing operation: Construction in winter with protective measures and relocation of existing building services.","breadcrumb":{"@id":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/#primaryimage","url":"https:\/\/daterra.de\/wp-content\/uploads\/2026\/04\/F90_Brandwand.webp","contentUrl":"https:\/\/daterra.de\/wp-content\/uploads\/2026\/04\/F90_Brandwand.webp","width":800,"height":600,"caption":"F90 Brandwand"},{"@type":"BreadcrumbList","@id":"https:\/\/daterra-gmbh-98pq1olwan.live-website.com\/errichtung-f90-brandwand\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/daterra.de\/"},{"@type":"ListItem","position":2,"name":"Brandschutz-Expertise im Rechenzentrum \u2013 Errichtung einer F90 Brandwand im laufenden Betrieb"}]},{"@type":"WebSite","@id":"https:\/\/daterra.de\/#website","url":"https:\/\/daterra.de\/","name":"Daterra Datacenter Solutions GmbH","description":"Sustainable. Efficient. Competent.","publisher":{"@id":"https:\/\/daterra.de\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/daterra.de\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/daterra.de\/#organization","name":"Daterra Datacenter Solutions GmbH","url":"https:\/\/daterra.de\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/daterra.de\/#\/schema\/logo\/image\/","url":"https:\/\/daterra.de\/wp-content\/uploads\/2026\/03\/Daterra_Logo-2.png","contentUrl":"https:\/\/daterra.de\/wp-content\/uploads\/2026\/03\/Daterra_Logo-2.png","width":580,"height":191,"caption":"Daterra Datacenter Solutions GmbH"},"image":{"@id":"https:\/\/daterra.de\/#\/schema\/logo\/image\/"}},{"@type":"Person","@id":"https:\/\/daterra.de\/#\/schema\/person\/ef19e68fcacaf8c388fddd7349562d1d","name":"s.kasprzyk","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/44fc54a0422931acf7970831a509dac2cc2d887f75e2fff4e0a12e08e6bc5d36?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/44fc54a0422931acf7970831a509dac2cc2d887f75e2fff4e0a12e08e6bc5d36?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/44fc54a0422931acf7970831a509dac2cc2d887f75e2fff4e0a12e08e6bc5d36?s=96&d=mm&r=g","caption":"s.kasprzyk"},"sameAs":["https:\/\/daterra.de"]}]}},"_links":{"self":[{"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/posts\/877","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/comments?post=877"}],"version-history":[{"count":25,"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/posts\/877\/revisions"}],"predecessor-version":[{"id":2840,"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/posts\/877\/revisions\/2840"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/media\/2129"}],"wp:attachment":[{"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/media?parent=877"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/categories?post=877"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/daterra.de\/en\/wp-json\/wp\/v2\/tags?post=877"}],"curies":[{"name":"WP","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}